Construction contract law since 2018
New Property Developer Contract Law 2018
The changes introduced by the new construction contract law came into force on 1 January 2018. They apply to all contracts notarised from that date.
This page sets out the eight most important changes for property developer contracts (Bauträgerverträge). Open an item to read the text.
If the buyer refuses to accept the property despite its completion, the seller may call upon the buyer to accept it within a reasonable period set by the seller. If the buyer does not accept the property within that period, the same legal consequences apply as for acceptance. The buyer can prevent this only by refusing acceptance and stating at least one defect. It has not yet been clarified whether the defect must be a material one or whether a minor defect is sufficient. In a property developer contract with a consumer (that is, a buyer purchasing for private purposes), the developer must, when calling upon the buyer to accept, inform the buyer at least in text form (an e-mail is sufficient) of the consequences of failing to declare acceptance or of refusing acceptance without stating defects.
Section 650g (1) to (3) (in conjunction with Section 650u (1) sentence 2) of the German Civil Code (BGB) now governs the developer’s right to have the condition of the property recorded where the buyer refuses to accept it. The procedure and the legal consequences are set out there as follows:
(1) 1If the customer refuses acceptance and states defects, the customer must, at the contractor’s request, take part in a joint recording of the condition of the work. 2The joint recording of the condition should state the date on which it was prepared and must be signed by both parties to the contract.
(2) 1If the customer fails to attend an agreed date for recording the condition, or a date set by the contractor within a reasonable period, the contractor may also record the condition unilaterally. 2This does not apply if the customer’s absence is due to a circumstance for which the customer is not responsible and which the customer has notified to the contractor without delay. 3The contractor must state the date on which the unilateral recording was prepared, sign it and provide the customer with a copy of it.
(3) 1If the work has been transferred to the customer and an obvious defect is not stated in the recording of the condition under subsection (1) or (2), it is presumed that the defect arose after the recording of the condition and is the customer’s responsibility. 2The presumption does not apply if, by its nature, the defect cannot have been caused by the customer.
The new law on property developer contracts regulates in more detail the requirements for the content of the construction specification (Baubeschreibung). It must describe the essential characteristics of the property clearly (Article 249 Section 2 (1) sentence 1 of the Introductory Act to the German Civil Code (EGBGB)) and contain at least the following information (sentence 2):
- a general description of the building to be constructed or the conversion work to be carried out, where applicable the type of house and method of construction,
- the nature and scope of the services offered, where applicable of the planning and site supervision, the work on the plot and the site set-up, and the stage of completion,
- building data, plans showing rooms and floor areas as well as elevations, floor plans and sections,
- where applicable, details of the energy, fire protection and sound insulation standards and of the building physics,
- details describing the structural elements of all essential trades,
- where applicable, a description of the interior fittings,
- where applicable, a description of the building services installations,
- details of the quality features that the building or the conversion must meet,
- where applicable, a description of the sanitary fixtures, fittings, electrical system, installations, information technology and external works.
The construction specification should be as detailed and precise as possible so that all parties are clear about all the services owed and the quality standards. As regards sound insulation, the description should not merely refer to a standard such as DIN 4109, but should describe the sound insulation standard specifically. Plans should always state floor areas. It is sufficient for the construction specification to refer to the division plans contained in the declaration of division (Teilungserklärung).
A construction specification is required even where the building has already been completed and the buyer can therefore inspect the property.
The developer must make the construction specification available to the buyer in good time before the contract is concluded. For this purpose, it is sufficient if the notary, as before, sends the buyer the draft contract together with all annexes and referenced deeds (which also include the construction specification), observing the two-week period.
Of course, the parties to the contract may agree individual deviations from the construction specification in the contract. These too should be drafted as precisely as possible. The notary must likewise send the buyer the contract with the agreed deviations at the latest two weeks before the date of the notarisation.
Where the construction specification is incomplete or unclear, the contract must be interpreted taking into account all circumstances accompanying the contract, in particular the standard of comfort and quality evident from the remainder of the description of services. Pre-contractual statements, advertising claims and depictions in brochures must also be taken into account. In case of doubt, the developer therefore owes a standard that corresponds to the other trades and to the quality agreed and/or advertised. In the developer’s own interest, the construction specification should be drafted as precisely as possible in order to create clarity about the scope and quality standard of all services owed.
Under the new law, the construction specification must contain binding information on the date of completion of the property. The developer may specify different completion dates for the individually owned property (Sondereigentum) and the jointly owned property (Gemeinschaftseigentum), in particular external works. If the start of construction has not yet been fixed, the duration of the construction work must be stated (Article 249 Section 2 (2) EGBGB). Until now it was customary to fix the completion date not in the construction specification but in the contract itself. This practice can probably be retained, since the buyer is just as well informed in this way and the completion date becomes binding for the buyer.
Under the new Section 632a (1) sentence 1 BGB, the contractor may demand from the customer “a payment on account in the amount of the value of the services it has performed and which are owed under the contract”. Under the likewise new Section 309 no. 15 BGB, the developer may not agree in contracts to any instalment payments “that are substantially higher than the payments on account to be made under Section 632a (1) […]”. It is currently disputed whether this new rule applies only to pure construction contracts or also to property developer contracts. In part it is assumed that the percentages under the Ordinance on Estate Agents, Property Developers and Construction Supervisors (MaBV) (binding under Section 650v BGB, Article 244 EGBGB) are special rules for the property developer contract, and that the new provisions in Section 632a (1) sentence 1 and Section 309 no. 15 BGB are not to apply alongside them. Others take the view that both sets of rules (the MaBV as well as Sections 632a (1) sentence 1 and 309 no. 15 BGB) are applicable side by side.
If one assumes that both sets of rules are applicable side by side, this means the following: the individual instalments that the buyer has to pay under the property developer contract must not substantially exceed the value actually provided for the individual service. The usual percentages provided for in Section 3 (2) MaBV cannot then simply be used as a basis by the developer where the value ratio of the individual services deviates considerably from them. If this cannot yet be foreseen when the contract is concluded, the parties may agree in the contract that the developer may demand the purchase price in seven instalments, made up of the individual instalments provided for in Section 3 (2) MaBV, with the developer undertaking to comply with the requirements of Section 632a (1) BGB.
Unlike before, the new law no longer allows the buyer, under any circumstances, to terminate the construction-contract part of the contract in isolation and to keep the purchase of the plot. The buyer can only ever withdraw from the contract as a whole. If there is an interest in being able to terminate part of the contract, the parties may grant the buyer an isolated right of termination for good cause (for example, where construction comes to a standstill).
Under the new Section 650n BGB, the developer is obliged to hand over to the buyer, before construction begins and upon completion, the documents that the buyer needs as proof to the authorities and to credit institutions:
(1) 1In good time before the start of the execution of a service owed, the contractor must prepare and hand over to the consumer the planning documents that the consumer needs in order to be able to prove to the authorities that the service will be performed in compliance with the relevant provisions of public law. 2This obligation does not exist to the extent that the consumer or a person commissioned by the consumer prepares the essential planning specifications.
(2) At the latest upon completion of the work, the contractor must prepare and hand over to the consumer the documents that the consumer needs in order to be able to prove to the authorities that the service has been performed in compliance with the relevant provisions of public law.
(3) Subsections (1) and (2) apply accordingly if a third party, such as a lender, requires proof that certain conditions have been met and if the contractor has raised the consumer’s justified expectation that those conditions will be met.
The documents required for credit institutions concern in particular the documents required for KfW funding.